GroundwaterRemediation.com: A technical resource forum for remediation of contaminated groundwater.
Groundwater-Remediation
GROUNDWATER REMEDIATION TECHNOLOGY OVERVIEW
GROUNDWATER REMEDIATION SPECIFICATIONS
GROUNDWATER REMEDIATION TECHNICAL ARTICES
GROUNDWATER REMEDIATION CASE HISTORIES
GROUNDWATER REMEDIATION INDUSTRY DIRECTORY
GROUNDWATER REMEDIATION EVENT CALENDAR
GROUNDWATER REMEDIATION JOBS
GROUNDWATER REMEDIATION DISCUSSION FORUMS
GROUNDWATER REMEDIATION ENGINEERS ESTIMATES
GROUNDWATER REMEDIATION TECHNICAL ASSITANCE
CONTACT GROUNDWATERREMEDIATIONS.COM
RETURN TO GROUNDWATERREMEDIATIONS.COM
GROUNDWATER REMEDIATION



GroundwaterRemediation.com: A technical resource forum for remediation of contaminated groundwater.
Print This Page!
GROUNDWATER REMEDIATION
CASE HISTORIES

US ARMY FUEL TERMINAL
Haines, Alaska


Over its operational lifetime, extensive soil and groundwater contamination had occurred at a now decommissioned US Army fuel terminal, located near Haines, Alaska, on the Lutak Inlet. In conjunction with other clean-up activities at the site, Remedial Construction Services, L.P. (RECON) was retained to install an air sparging system between a benzene-contaminated groundwater plume and the Inlet to treat the contaminant in-situ and thus halt offsite migration.

Air Sparging Technique
Air sparging involves the injection of clean air into the saturated subsurface soils to meet two objectives: increase microbial activity by the introduction of oxygen into the subsurface; and increase the volatilization of hydrocarbons by passing air through the contaminated groundwater (air stripping). The off gas is collected by means of a vacuum pump and either passed through a vapor phase treatment system that allows moisture to settle out and organics to be adsorbed by granular activated carbon, or it can be discharged, as was the case of this project.

Air sparging is particularly suited to the lighter gasoline components, such as benzene because they easily transfer from the dissolved to the vapor phase.

System Installation
The air sparging system was configured to maximize the efficiency of the system and consisted of a series of 10 injection point risers, manifolded at the top and connected to a blower. T-connectors at the injection point inverts were fitted with horizontal sparge piping extending 20 feet in either direction.

The system was installed using the biopolymer (BP) slurry trench method. The slurry exerts hydraulic pressure against the trench walls and acts as shoring to prevent collapse. BP slurry is biodegradable, and does not reduce the final permeability of the in-situ soil or backfill materials.

The 410-foot long trench was excavated through BP slurry to the top of bedrock, at up to 25 feet below working grade. Filter fabric was installed on both sides of the trench to minimize clogging. The air sparge system was then installed through the slurry, ahead of graded backfill placement.

Despite the adverse weather conditions typical of Alaska in the Fall season, the project was completed on schedule and without incident.

 

Back to Top
PILGRIM DRY CLEANERS
Houston, Texas


This project consisted of installing eight-groundwater treatment systems and four groundwater soil-vapor recovery systems at eight Pilgrim Cleaner facilities throughout the Houston area. Remedial Construction Services, L.P. (RECON) performed the work for Fluor Daniels GTI.

The scope of work at each site included procuring, excavating and installing:
  • Multiple traffic bearing road boxes for extraction wells and junction boxes.
  • Groundwater containment piping from recovery wells to remediation building.
  • Four-inch diameter contingency line from the remediation equipment compound to the high-vacuum extraction wells
The work at each site also included:
  • Providing and installing a recovery hose and an air hose through the containment piping from the remediation equipment buildings to the recovery wells.
  • Connecting the effluent line of the remediation equipment compound to the existing clean out at the existing sanitary sewer.
  • Constructing a trench for the piping, backfilling and resurfacing.
  • Installing a 15-foot reinforced concrete leveling slab for the equipment skid.
  • Installing an 8-foot high chain-link fence with privacy slats around the slab.
  • Installing Owner-furnished remediation equipment.
  • Connecting all electrical equipment between the main power connection nd the remediation equipment compound.
Back to Top

GROUNDWATER/SOIL VAPOR EXTRACTION RECOVERY SYSTEM
Navasota, Texas


Remedial Construction Services, L.P. (RECON) was contracted to construct a groundwater and soil vapor extraction recovery system to remove hydrocarbon contamination from the subsurface groundwater and underlying soils. The area of removal encompassed the a Diamond Shamrock retail fueling station.

RECON installed 1,600 linear feet of PVC groundwater recovery piping and 1,000 linear feet of PVC vapor extraction piping to 35 onsite and offsite recovery wells. The existing pavement was saw-cut, to an average depth of 8-inches and  removed in order to excavate the trenches for the recovery system piping.

Using conventional open-trench construction most of the onsite and offsite piping was installed. Piping that crossed the State Highway was installed using a directional boring technique. This method was chosen due to the offsite locations of some of the recovery piping in the Texas Department of Transportation (TxDOT) easement, which would minimize traffic disruptions.

RECON installed a portable recovery treatment system composed of an air stripper, oil/water separator, carbon vessels along with electrical pump motors and blowers with controls.

A major hurdle on this project, was the installation of the recovery system piping underneath and through the median of State Highway 105 and working in the TxDOT right-of-way.

Back to Top
pagebottom001.gif - 2639 Bytes
GROUNDWATER REMEDIATION TECHNOLOGY OVERVIEW | GROUNDWATER REMEDIATION SPECIFICATION | GROUNDWATER REMEDIATION TECHNICAL ARTICES | GROUNDWATER REMEDIATION CASE HISTORIES | GROUNDWATER REMEDIATION INDUSTRY DIRECTORY | GROUNDWATER REMEDIATION EVENT CALENDAR | GROUNDWATER REMEDIATION JOBS | GROUNDWATER REMEDIATION DISCUSSION FORUMS | GROUNDWATER REMEDIATION ENGINEERS ESTIMATES | GROUNDWATER REMEDIATION TECHNICAL ASSITANCE | CONTACT GROUNDWATERREMEDIATION.COM | GROUNDWATER REMEDIATION HOME | SITE MAP | RETURN TO GROUNDWATERREMEDIATION.COM




WWW.TEKTRACKER.COM | WWW.AUGERCASTPILES.COM | WWW.BIOPOLYMERTRENCH.COM | WWW.DEEPFOUNDATIONS.COM | WWW.DEEPSOILMIXING.COM | WWW.DIAPHRAGMWALL.COM | WWW.GROUNDWATERREMEDIATION.COM | WWW.JET-GROUTING.COM | WWW.PERMEABLEREACTIVEBARRIER.COM | WWW.SECANTPILE.COM | WWW.SEDIMENTCAP.COM | WWW.SHEETPILE.COM | WWW.SLUDGESTABILIZATION.COM | WWW.SLURRYWALL.COM | WWW.SOIL-MIXING.COM | WWW.SOILMODIFICATION.COM

© 2005 www.tektracker.com | Site Design by: eNet Technologies